• Blog
  • About
Leslie RollingLeslie Rolling
Leslie RollingLeslie Rolling
  • Blog
  • About

Honey We’re Home: Let’s Get Started!

January 21, 2015 3 Comments

Back in November when I launched this baby I put up my first post in my “Honey We’re Home” section that’s set aside to follow the process as we develop and build the new mission property. It was SO exciting to be starting the process, even if it was just the getting ready kinds of things.

Well, here we are almost two months later and there’s progress to share! It’s my goal is to do at least one post per month as an update, but I have a feeling there will be quite a few more in between as things really start moving, especially with the house.

A lot of people are familiar with wood frame construction because that’s what happens all around you whenever anyone is building a house, but concrete construction is a whole different ball game. It’s definitely more permanent in nature so every decision we make in the planning stages needs to be really well thought out. It’s VERY hard to get 5-10 years in and decide to take down a wall. Structurally things are entirely different too, because concrete is so much heavier. Also, we’ve seen the effects of a devastating earthquake 5 years ago, and while we didn’t see much damage in our area, Haiti is right over several fault lines and has now been deemed an earthquake zone and we need to plan accordingly. We’re very grateful for our engineer friend. He does a lot of government contract work, including military grade stuff, and I’ll admit, we kind of thought it was overkill when he kept insisting on LOTS of re-bar during our last construction project. But, as I sat at my desk while the earth shook and not a single thing fell off the walls I was VERY grateful and we’re once again following his recommendations because we know it’s worth it in the long run.

So, where are we at now?!?

Our original plan was to start with the house and office, but because of some hold ups for our engineer friend we decided to go ahead with the work yard area. More specifically, the main shop and storage area, staff bathrooms, and the main filter construction area.

I should take a minute to give you some background on our current situation vs. what we’re aiming for.

Right now at the current mission site our property is cut in half by a government ease way. The residence part is on one side while the work yard is on the other.

The work yard has a shop area (depot in Creole/French) where we house our generator, inverters and battery system. In this area we also store all our tools, equipment for welding and other work, and filter construction supplies. There’s a covered work area in front where the guys weld our molds, and right next to it is the area where we wash, dry and bag sand and gravel for filter installations. Because these areas are together there’s literally sand everywhere.

The filter production area is in another area of the yard, but is uncovered. There are some shade trees, but the sun moves through the day. We’ve talked about building a covered area, but since we’d bought the new property we didn’t want to invest in the project when we knew we would be moving eventually. All in all it’s fine. We degaje (a really great word that means “make do”) by hanging tarps, but it’s not ideal. We’re also growing and running out of room. This year will mark the 14th year that Clean Water for Haiti has been in operation. Right now we will max out our space with about 200 filters produced each month. At the new site we’ll have the room to build a work space that will allow us to produce up to 400 filters per month.

The new property has enough room that we’ll be able to spread things out and give each part of our program it’s own area. To give you an idea of how the property will be developed here’s a little diagram I made up that we’ve used in fundraising and promotion efforts:

Property Plan Photo

In the past two months the construction team, made up of some of our regular staff as well as hired contractors, has made good headway on the filter production area. In December all the foundation trenches were dug. We were originally planning on hiring a backhoe to dig all of this, but the time it would have taken to find one and make arrangements became an issue and our team was ready to go, so we did the digging by hand. They’re amazing!

20141204-_MG_8793-5

Re-bar was tied for the support posts that will hold the roof for the covered work area. This is one of our biggest changes at the new site and we’re so excited about it! As I mentioned, right now the guys build filters in the sun, or whatever shade we can get from an overhead tarp. Caribbean sun is HOT, especially in the summer months. They work really hard. And we love them. So, we want to be very intentional about providing a work space that is not only functional, but pleasant to work in. We want them to know that we really, truly appreciate all their hard work, and them specifically.

The new work area will be a 30×60′ pad with a roof over it. The roof will be about 15′ high, so lots of air movement. Not only will it shade the workers, but it will actually help provide stronger filters because the cement will be able to cure more slowly. When the filters are drying in the sun it can speed the process up too much and cause cracking later on. So, less waste, and donor dollars will go further. Because we’ll have a roof we’ll be able to install industrial ceiling fans, which is such a fun thing to be able to do for the guys. Along with good air movement it will also help keep the work area dry. We use a lot of water, and right now it just soaks into the ground, but because we’ll be using a cement pad we’ll need to have good drainage and air flow to keep things dry.

In the past two weeks the foundation of the shop was done.

20150115-_MG_9136-13 (Large)It’s all done by hand. They mix the mortar in the cement mixer, put it in the hole, then place rocks. The rocks, if they aren’t the right size, get broken into smaller chunks by hand with a small sledge hammer.

20150115-_MG_9131-8 (Large)

Before the rocks are put in the mortar they get wet down. This helps them adhere to the mortar better and it slows the drying process so the foundation doesn’t crumble.

20150115-_MG_9132-9 (Large)

The re-bar forms for the roof support columns has been placed and the footings have been poured.

20150115-_MG_9139-16 (Large)

Trenches for running the electrical and plumbing conduit from the generator and power center have been dug.

20150115-_MG_9123-1 (Large)Electrical and plumbing conduit was laid in the foundation before it was done.

20150115-_MG_9135-12 (Large)

That’s the progress as of last week. I need to go out later this week and take some new pictures. I’m trying to do it weekly so we have photo progress to look back on and because we can use these photos to show mission supporters as we go, but it also means I can share them with you!

~Leslie

Share with a friend!

  • Click to email a link to a friend (Opens in new window) Email
  • Click to print (Opens in new window) Print
  • Click to share on Facebook (Opens in new window) Facebook
  • Click to share on X (Opens in new window) X
  • Click to share on Pinterest (Opens in new window) Pinterest
  • More
  • Click to share on LinkedIn (Opens in new window) LinkedIn
  • Click to share on Reddit (Opens in new window) Reddit
  • Click to share on Pocket (Opens in new window) Pocket
  • Click to share on Tumblr (Opens in new window) Tumblr
3 Comments
Share
0

3 Comments

Leave your reply.
  • Barb Jonusaitis
    · Reply

    January 21, 2015 at 12:24 PM

    Yea Rebar!!!!!!

    Could you mark N on the chart?
    How long is a side of the plot?
    Is the plot flat?
    Will the solar array provide shade for the house?
    Is the house two stories?

    Nice report Leslie, I look forward to the future ones.

    • Leslie
      · Reply

      Author
      January 21, 2015 at 12:55 PM

      Ha ha! So many questions :)

      The diagram is actually set up so the top is north and driveway entrance is south :) It’s about an acre total space. The plot IS flat and has a very slight decline towards the NW corner, about 3 feet difference in elevation from the SE driveway corner, I think. Yes, the solar panels will be on top of the main house. Both the house and the guest house will be two stories, and each building will have it’s own water tank and solar water heater.

  • Theresa Cledomin
    · Reply

    January 23, 2015 at 3:26 AM

    so so excited for you guys!! So fun to be able to follow on your journey to the new land…

    And how wonderful for the staff to have a covered area to work in – I am sure they will be looking forward to that!

    looking forward to more photos and future updates

I love to hear from you! Thanks for taking the time to share your thoughts.Cancel reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

I’m Leslie. I started my blog back in 2005 when I was fresh off the plane in Haiti. I lived in Haiti for over 17 years as a missionary, wife, and eventually mom. My husband and I ran Clean Water for Haiti together, day in and day out. We carved out a life we loved doing something important to us. Sadly, in the fall of 2022 we had to make the difficult decision to leave Haiti because of the insecurity. We’re now settling into life in the US. I’m thankful that I get to continue my work with CWH as the Executive Director for Canada and the US.

Search

See What You’ve Missed

Subscribe to the Blog

Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Join 159 other subscribers

Contact Me

Have a question, thought or comment? I love to hear from people!

Send

© 2025 — Leslie Rolling